Previous revision
3135 [2024/03/27 12:05] sigridundset3135 [2024/04/06 09:17] (current) sigridundset
Line 1: Line 1:
 ====== 3135 345kV ====== ====== 3135 345kV ======
 +
 +{{ :may_18_2023_e_pac_lines_map.png?linkonly |map showing line location}}
  
 {{ :3135:a-126_s-153_3135.pdf |2023, June 3, withdrawn DES permit application for construction}} {{ :3135:a-126_s-153_3135.pdf |2023, June 3, withdrawn DES permit application for construction}}
Line 17: Line 19:
 {{ ::2-cr-2021-020-petition.pdf |2021, November 12: petition for crossing Great Bog, structures 105 and 106, "The 3135 Line’s existing three conductors, one static wire and one OPGW communications wire, whose specifications are identified on the Exhibit 4 Cable Schedule, will be unchanged in the course of relocation to the new replacement structures"}} {{ ::2-cr-2021-020-petition.pdf |2021, November 12: petition for crossing Great Bog, structures 105 and 106, "The 3135 Line’s existing three conductors, one static wire and one OPGW communications wire, whose specifications are identified on the Exhibit 4 Cable Schedule, will be unchanged in the course of relocation to the new replacement structures"}}
  
-{{ ::20-103_2020-08-14_staff_rec.pdf |2020, August 14: staff recommendation and exhibits. "The structure will have conductors for the 345 kV 3195 transmission line consisting of (3) 850.8 kcmil ACSR 45/7 cables. The fiber optic cables consisting of (1) 48 Fiber OPGW and (1) 84 Fiber OPGW will be vertically attached above the conductors }}+
3135.1711555559.txt.gz · Last modified: 2024/03/27 12:05 by sigridundset