 C-196 C-196
  
 +{{ :may_18_2023_e_pac_lines_map.png?linkonly |map showing line location}}
  
 {{ ::a04_es_asset_condition_wood_structure_replacements.pdf |2023, January 19, presentation to PAC, 29 out of 145 structures replaced, $6.2 m.}} {{ ::a04_es_asset_condition_wood_structure_replacements.pdf |2023, January 19, presentation to PAC, 29 out of 145 structures replaced, $6.2 m.}}
Line 7: Line 7:
 {{ ::c196_-_q171_-_a253_des_permit_with_waivers.pdf |2023, January 9 DES permit with waivers from requirements of Env-Wq 1503.12(d)(1), Env-Wq 1503.21(d)(6) and (7), and Env-Wq 1504.09}} {{ ::c196_-_q171_-_a253_des_permit_with_waivers.pdf |2023, January 9 DES permit with waivers from requirements of Env-Wq 1503.12(d)(1), Env-Wq 1503.21(d)(6) and (7), and Env-Wq 1504.09}}
  
-{{ ::c196_-_a252_-_q171_des_to_gza_.pdf |2023, January 16: DES and GZA email}} +{{ ::c196_-_a252_-_q171_des_to_gza_.pdf |2023, January 9-16: DES and GZA emails}}
- +
-{{ ::c196_-_a252_-_q171_des_to_gza_.pdf |2023, January 5: DES and GZA email}}+
  
 {{ ::c196_-_m108_-_h137_-_g146_wildlife_protection_plan.pdf |2023, April 28: Wildlife protection plan}} {{ ::c196_-_m108_-_h137_-_g146_wildlife_protection_plan.pdf |2023, April 28: Wildlife protection plan}}
Line 18: Line 16:
  
 {{ ::c196_-_a253_aot_application.pdf |2022, November 28: AOT application}} {{ ::c196_-_a253_aot_application.pdf |2022, November 28: AOT application}}
 +
 +{{ :c196:c-196_tca_app.pdf |2022, September 20: application for TCA}}
  
 {{ ::c196_-_q171_cover_page_aot.pdf |2022, September 9: AOT transmittal cover page}} {{ ::c196_-_q171_cover_page_aot.pdf |2022, September 9: AOT transmittal cover page}}
Line 29: Line 29:
 {{ ::c196:3-cre-2022-018-energy-staff-recommendation.pdf |2022, July 27: staff recommendation}} {{ ::c196:3-cre-2022-018-energy-staff-recommendation.pdf |2022, July 27: staff recommendation}}
  
-{{ ::c196:1-cre-2022-018-petition.pdf |2022:July 22: E$ petition for river crossing}}+{{ ::c196:1-cre-2022-018-petition.pdf |2022:  July 22: E$ petition for river crossing; "Also as part of the Greggs substation improvements, the C196’s existing three 795 ACSR 36/1 conductors will be replaced with 1272 ACSS 54/19 conductor. The OPGW and static wires between Structures 143 and 144 will be unchanged in the course of relocation to the replacement steel structure."}}
  
-{{ ::c196:2-cre-2022-018-petition-attachments.pdf |2022, petition attachments}}+{{ ::c196:2-cre-2022-018-petition-attachments.pdf |2022, petition attachments; one .646 96 fiber OPGW and one 19#10 Alumoweld}}
  
 {{ ::c196_q171_surface_and_groundwater_resources_6-28-2022.pdf |2022, June 28: Surface and Groundwater resources}} {{ ::c196_q171_surface_and_groundwater_resources_6-28-2022.pdf |2022, June 28: Surface and Groundwater resources}}
  
 {{ ::c196:a3_eversource_new_hampshire_asset_conditions_wood_structure_replacement.pdf |2022, June 15: presentation to PAC}} {{ ::c196:a3_eversource_new_hampshire_asset_conditions_wood_structure_replacement.pdf |2022, June 15: presentation to PAC}}
 +
 +{{ :c196:c-196_2010-10-15_nhpuc_order_no_25_157-order_nisi_granting_a_license.pdf |2010, October 15: Order nisi }}
 +
 +{{ :c196:c-196_2010-10-15_staff_memo_recommendation.pdf |2010, October 15: Staff recommendation}}
 +
 +{{ :c196:c-196_2010-09-30_psnh_revised_petition_for_license_for_cable_across_glen_lake_goffstown_nh.pdf |2010, September 30; revised petition for crossing Glen Lake, Goffstownhe C- 196 line as presently constructed
 +and licensed by the Commission, crosses Glen Lake with 3 phase wires and two static wires. PSNH proposes to replace one of the static wires with an optical ground wire (OPGW).; "The C- 196 line as presently constructed and licensed by the Commission, crosses Glen Lake with 3 phase wires and two static wires. PSNH proposes to replace one of the static wires with an optical ground wire (OPGW)."}}
 +
 +{{ :c196:c-196_2010-09-03_psnh_petition_for_license_for_cable_across_glen_lake_-goffstown_nh.pdf |2010, September 3: petition for crossing Glen Lake; The structures have also been determined to be able to accept the increased loads imparted by the larger cable diameter...The static wire (OPGW cable) will be carried on the structure by a support
 +bracket at the top of the crossarm and is approximately 7-ft 6-in up vertically from the
 +phase wire." }}
 +
 +{{ :c196:c-196_6-6-1975_glen_lake_crossing.pdf |1975, June 6: petition for crossing Glen Lake; "reconstruct two parallel 115 KV electric transmission lines of wires and cables over and across Glen Lake in the Town of Goffstown, New Hampshire, which are part of its 115KV system connecting the Greggs Substation in Goffstown and the Merrimack Substation in Bow;"}}
 +
 +
  
  