Both sides previous revisionPrevious revisionNext revision | Previous revision |
d-142 [2023/10/26 02:09] – sigridundset | d-142 [2025/02/10 01:59] (current) – sigridundset |
---|
D-142 115kV Line | D-142 115kV Line |
| |
| {{:d142:d-142_michels_site.png?linkonly|2024: Post-construction photo from Michel's site}} |
| |
| {{:d142:d-142_michels_site_2.png?linkonly |2024: Construction photo from Michel's site}} |
| |
| {{ :d142:d-142_michels_site_1.png?linkonly |2024: Construction photo from Michel's site}} |
| |
| {{ ::2023_11_15_topac_lsp_eversource_presentation.pdf |2023, November 15: Eversource TOPAC (Transmission Owners Planning Advisory Committee presentation to PAC}} |
| |
{{ ::d142-project-introduction-21.pdf |2022, August 31: "Dear Neighbor" construction is now complete letter}} | {{ ::d142-project-introduction-21.pdf |2022, August 31: "Dear Neighbor" construction is now complete letter}} |
| |
{{ ::d142-construction-factsheet.pdf |2022, January: Project Overview}} | {{ ::22-049_2022-08-24_eversource_att-pet-approval-financing-transaction.pdf |2022, June 30: complete DE-22-049 document listing E$ proposed spending}} |
| |
| {{ ::d142-construction-factsheet.pdf |2022, January: Project Overview flyer}} |
| |
{{ ::attachment_rr-dpu-es-3.pdf |2022, October 19: PAC presentation, local system plan}} | {{ ::attachment_rr-dpu-es-3.pdf |2022, October 19: PAC presentation, local system plan}} |
| |
| {{ ::crossing-license-granted.pdf |2021, December 15: crossing granted}} |
| |
{{ ::cr-2021-017-order-of-notice.pdf |2021, November 22: order of notice}} | {{ ::cr-2021-017-order-of-notice.pdf |2021, November 22: order of notice}} |
| |
{{ ::cre_2021-009-crossing-engy-recommendation.pdf |2021, September 2021: Staff recommendation}} | {{ ::staff_recommendation_d-142.pdf |2021, October 27: Staff recommendation}} |
| |
{{ ::crossing-license-granted.pdf |2021, December 15: crossing granted}} | {{ ::crossing_petition_d-142.pdf |2021, October 22: E$ crossing petition}} |
| |
| {{ ::exhibits_1_2_-_strs._95_96.pdf |2021, October 20: crossing exhibits}} |
| |
{{ ::d142-cr2021-009-order-of-notice.pdf |2021, September 28: order of notice}} | {{ ::d142-cr2021-009-order-of-notice.pdf |2021, September 28: order of notice}} |
| |
{{ ::21-085_2021-04-28_eversource_petition_crossing_northumberland_lancaster.pdf |2021, April 28: crossing petition including Cape Horn State Park}} | {{ :d142:d-142_des_permit_aot2007_rm.pdf |2021, September 6: DES permit with waivers "DES granted approval to waiving specific requirements of Env-Wq 1504.09, finding that the development of a stormwater drainage report, and associated drainage area plans and hydrologic soil group plans was not warranted given the scope of the project, its linear nature, and the relatively minor area of impervious surfaces constructed. It was further determined that granting the waivers would not have an adverse impact on the environment, public health, public safety, or abutting properties, and that granting the requests is consistent with the intent and purpose of the rules waived." }} |
| |
{{ ::6080504dc8621.pdf.pdf |2021, April 12: Caledonian Record article}} | {{ ::cre_2021-009-crossing-engy-recommendation.pdf |2021, September 2021: Staff recommendation}} |
| |
{{ ::d142-project-fact-sheet.pdf |2021. April: Project Overview}} | {{ :d142:d142_aot_permittingplans_20210901_1.pdf |2021, September 1: permitting plans 1}} |
| |
{{ ::d-142_damage_and_misrepresentation.pdf |}} | {{ :d142:d142_aot_permittingplans_20210901_2.pdf |2021, September 1: permitting plans 2}} |
| |
{{ ::d-142_more_untruths.pdf |}} | {{ :d142:d142_aot_permittingplans_20210901_3.pdf |2021, September 1: permitting plans 3}} |
| |
{{ ::exhibits_1_2_-_strs._95_96.pdf |exhibits}} | {{ :d142:d142_aot_permittingplans_20210901_4.pdf |2021, September 1: permitting plans 4}} |
| |
{{ :attachment_rr-dpu-es-3.pdf |attachment}} | |
| |
{{ :iso_7-15-2021_no_significant_impact_of_interconnection.pdf 2021, July 15: no impact if interconnected}} | {{ :iso_7-15-2021_no_significant_impact_of_interconnection.pdf |2021, July 15: no impact if interconnected}} |
| |
| {{ ::d142:d142_aot_application_20210907_final_part1.pdf |2021, June 2: AoT application 1}} |
| |
| {{ :d142:d142_aot_application_20210907_final_part_2.pdf |2021, June 2 AoT application 2}} |
| |
| {{ ::21-085_2021-04-28_eversource_petition_crossing_northumberland_lancaster.pdf |2021, April 28: crossing petition including Cape Horn State Park}} |
| |
| {{ ::6080504dc8621.pdf.pdf |2021, April 12: Caledonian Record article}} |
| |
{{ ::staff_recommendation_d-142.pdf |Staff recommendation}} | {{ ::d142-project-fact-sheet.pdf |2021, April: Project Overview flyer}} |
| |
{{ ::crossing_petition_d-142.pdf |crossing petition}} | {{ :d142:d-142_1557.pdf |2020, December 18: mowing permit des}} |
| |
{{ ::a7_eversource_lsp.pdf |October 2019 PAC presentation local system plan}} | {{ ::a7_eversource_lsp.pdf |2019, October : PAC presentation local system plan}} |
| |
{{ ::d-142.png?linkonly |2015: Northern Pass planned to upgrade the D-142 line (336) to only 795, not the 1272 that it has constructed.}} | {{ ::d-142.png?linkonly |2015: Northern Pass planned to upgrade the D-142 line (336) to only 795, not the 1272 that it has constructed.}} |