g-146

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
g-146 [2023/10/21 04:05] sigridundsetg-146 [2024/07/09 03:36] (current) sigridundset
Line 1: Line 1:
-G-146 $58 m. Not on June 2023 Asset Condition Project list+G-146 $58 m. 
  
 +
 +{{ :g146:g-146_hearing.pdf |2024, June 14: "The New Hampshire Department of Environmental Services Wetlands Bureau (NHDES) is providing notice of a public hearing scheduled for June 21, 2024, commencing at 9:30am."}}
 +
 +{{ :g146:g-146_to_applicant.pdf |2024, June 14: DES to E$, "Standard Dredge and Fill Wetlands Permit Application (RSA 482-A): Notice of Public Hearing Cover Letter NHDES File Number: 2024-00515"}}
 +
 +{{ :g146:g-146.pdf |2024, May 14: "Request for More Information – Standard Dredge and Fill Wetlands Permit Application (RSA 482-A) NHDES File Number: 2024-00515"
 +
 +{{ :g146:g-146_more.pdf |2024, February 9: "Administrative Completeness Notice – Standard Dredge and Fill Wetlands Permit Application (RSA 482-A) NHDES File Number: 2024-00515"}}
 +
 +{{ :draft_project_list_presentation-oct_2023.pdf |2023, October: RSP asset condition list}}
  
 {{ ::c-189_g146_h137_m108_maps.pdf |August 2, 2023 Environmental Resources maps}} {{ ::c-189_g146_h137_m108_maps.pdf |August 2, 2023 Environmental Resources maps}}
 +
 +{{::6-15-2023_pac_meeting.png?linkonly|2023, June 15 PAC minutes}}
 +
 +{{ :g146:g-146_petition.pdf |2023: petition for crossing}}
 +
 +{{ :g146:g-146_2023-012-application-exhibits.pdf |2023: crossing exhibits}}
  
 {{ :a05_2023_06_15_pac_laminated_wood_structure_replacements_phase_3.pdf |June 2023 PAC presentation}} {{ :a05_2023_06_15_pac_laminated_wood_structure_replacements_phase_3.pdf |June 2023 PAC presentation}}
 +
 +{{ :c189:m108_-_h137_-_c189_-_g146_start_of_construction_form.pdf |2023, May 22: Start of Construction form}}
  
 {{ ::c189_-_m108_-_h137_-_g146_des_permit_with_waivers.pdf |2023, May 22: DES permit waiving {{ ::c189_-_m108_-_h137_-_g146_des_permit_with_waivers.pdf |2023, May 22: DES permit waiving
Line 17: Line 35:
 {{ :c189:m108_-_h137_-_c189_-_g146_aot_application_checklist.pdf |2023, February 1: AoT application checklist}} {{ :c189:m108_-_h137_-_c189_-_g146_aot_application_checklist.pdf |2023, February 1: AoT application checklist}}
  
 +{{ :c189:c189_-_m108_-_h137_-_g146_aot_application.pdf |2023, January 27: AoT application}}
  
 {{ ::g-146.pdf |G-146: Why are we doing this?}} {{ ::g-146.pdf |G-146: Why are we doing this?}}
 +
 +{{ ::k165_p145_.pdf |2016, January 7: TCA approval, apparently reliability}}
  
 {{ ::v-182_and_g-146_2015.png?linkonly |2015 Testimony Northern Pass}} {{ ::v-182_and_g-146_2015.png?linkonly |2015 Testimony Northern Pass}}
 +
 +{{ :g146:g-146_proposed_reliability_uprate_10-2012.png?linkonly |2012, October: Proposed reliability uprate}}
  
  