 +The S153 line originates in Stratham and ends in Portsmouth. It shares the easement with the A-126, and a gas line.
  
 {{ :may_18_2023_e_pac_lines_map.png?linkonly |map of project location}} {{ :may_18_2023_e_pac_lines_map.png?linkonly |map of project location}}
Line 17: Line 17:
 {{ ::a04_2023_05_28_pac_nh_wood_structure_and_opgw_installations.pdf |2023, May 18, presentation to PAC, replace 16 out of 51 structures; $5. million}} {{ ::a04_2023_05_28_pac_nh_wood_structure_and_opgw_installations.pdf |2023, May 18, presentation to PAC, replace 16 out of 51 structures; $5. million}}
  
-{{ ::2023_05_18_meeting_minutes_final.pdf |2023 may 18 PAC minutes}}+{{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes}}
  
 {{ ::s153:5-9-2023_a-126_h-141_s-153.pdf |2023, May 9: F&G permit conditions}} {{ ::s153:5-9-2023_a-126_h-141_s-153.pdf |2023, May 9: F&G permit conditions}}
  
-{{ :r193_-_a121_-_h141_aot_permit_application.pdf |2023, May 5 AoT application}}+{{ :a126:a126_-_h141_-_s153_aot_checklist.pdf |2023, April 3: AOT checklist}}
  
-{{ ::a126:aot-2412_miscellaneous_r.pdf |2023, May 5cover letter for Alteration of Terrain application. "The proposed project includes the replacement of 76 existing utility structures on the R193, A126, and H141 transmission lines that must be replaced because they have reached the end of their service life."}} +{{ :a126:a126_-_h141_-_s153_aot_.pdf |2023, March 22: Alteration of Terrain application. "New steel poles will be installed. Existing conductors and static wire will be transferred to new steel poles."}}
- +
-{{ :r193_-_a121_-_h141_aot_permit_application.pdf |2023, May 5; AoT application}} +
- +
-{{ :a126:a126_-_h141_-_s153_aot_checklist.pdf |2023, April 3: AOT checklist}}+
  
-{{ :a126:a126_-_h141_-_s153_aot_.pdf |2023, March 22Alteration of Terrain application}}+{{ :s153:s-153_cup_5-15-2023.pdf |2023, March 15Conditional Use Permit application for Greenland}}
  
  
  
  