====== U-199 115kV line ====== | ====== U-199 115kV line ====== |
| |
| |
| {{ :u199:24-087-2025-07-24-nhpuc-proc-order-re-mot-for-summary-resolution-of-proceeding.pdf |2025, July 24: PUC denies Eversource motion for summary waiver.}} |
| |
| {{ :u199:u-199_2025_and_2022.png?linkonly |2025, June: Google Earth U-199 2025 and 2022}} |
| |
| {{ :u199:24-087-2025-07-22-eversource-motion-summary-resolution-proceeding.pdf |2025, July 22: Eversource motion for summary waiver of Bethlehem's zoning.}} |
| |
| {{ :u199:doe_witness_contradicts_eversource_23-087_1.pdf |2025, June: DOE witness DeVergilio contradicts Eversource testimony}} |
| |
{{ :u199:24-087-2025-06-06-nhdoe-testimony-devirgilio-1.pdf |2025, June 6: DOE witness DeVergilio testimony in support of Eversource with no evidence presented.}} | {{ :u199:24-087-2025-06-06-nhdoe-testimony-devirgilio-1.pdf |2025, June 6: DOE witness DeVergilio testimony in support of Eversource with no evidence presented.}} |
| |
{{ :u199:24-087-2025-06-06-nhdoe-position-statement.pdf |2025, June 6: After pretending to oppose Eversource and support Bethlehem, NH DOE shows its true position as a captured agency}} | {{ :u199:24-087-2025-06-06-nhdoe-position-statement.pdf |2025, June 6: After pretending to oppose Eversource and support Bethlehem, NH DOE acts as a captured agency}} |
| |
{{ :u199:24-087-2025-06-06-nhdoe-att-testimony-devirgilio.pdf |2025, June 6: DeVergilio resume and more responses to questions.}} | {{ :u199:24-087-2025-06-06-nhdoe-att-testimony-devirgilio.pdf |2025, June 6: DeVergilio resume and more responses to questions.}} |
| |
{{:u199:pxl_20241221_160127285_2.jpg?linkonly|2024, December 21: construction}} | {{:u199:pxl_20241221_160127285_2.jpg?linkonly|2024, December 21: construction}} |
| |
| {{ :u199:u199-permitting-plans_2025-1.pdf |2024, October: permitting/construction plans}} |
| |
{{ :u199:cre-2024-007-license.pdf |2024, August 6: crossing license}} | {{ :u199:cre-2024-007-license.pdf |2024, August 6: crossing license}} |
{{ :u199:cre-2024-007-staff-recommendation.pdf |2024, August 5: Staff recommendation}} | {{ :u199:cre-2024-007-staff-recommendation.pdf |2024, August 5: Staff recommendation}} |
| |
{{ :u199:cre-2024-007-exhibits.pdf |2024, : Exhibits for crossings}} | {{ :u199:cre-2024-007-exhibits.pdf |2024: Exhibits for crossings dated 12/29/2023 and 12/2016}} |
| |
{{ :u199:cre-2024-007_u-199-application.pdf |2024, : Application for crossings}} | {{ :u199:cre-2024-007_u-199-application.pdf |2024, August 1: Application for crossings}} |
| |
{{ :u199:u199-structure-heights-littleton.pdf |2024: structure heights, Littleton, withheld for months by Eversource}} | {{ :u199:u199-structure-heights-littleton.pdf |2024: structure heights, Littleton, withheld for months by Eversource}} |
{{ ::u199-permitting-plans.pdf |2023, October 10: DRAFT permitting plans}} | {{ ::u199-permitting-plans.pdf |2023, October 10: DRAFT permitting plans}} |
| |
{{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026}} | {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795 ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026}} |
| |
{{ ::b112-u199-q195_rebuild_presentation.pdf |2023, May 18, presentation to PAC}} | {{ ::b112-u199-q195_rebuild_presentation.pdf |2023, May 18, presentation to PAC}} |