Previous revision
w-171 [2023/10/14 06:08] sigridundsetw-171 [2024/11/22 08:14] (current) sigridundset
Line 1: Line 1:
 W-179 115kV Line W-179 115kV Line
  
 +{{ ::eversource_2024_lsp_a.pdf |2024, November 20: Local System Plan, in-service, $64.5 m.}}
  
 +{{ :w179:w-179_dummer.pdf |2024, June 28: DES permit for wetlands impacts cover letter}}
  
-{{ ::w-179_des_permit_with_waivers.pdf |2023April 4: DES permit with waivers}}+{{::w179:w-179_6-28-2024_des_permit.pdf |2024June 28: DES permit "This is for the portion of a large-scale project where the installation of construction mats in wetlands exceeds one growing season for completion of the replacement of overhead static wires with optical ground wire."}}
  
-{{ ::w179-project-plans-maps.pdf |2023, March 29; Environmental Resources Construction Map Set}}+{{ ::2023_11_15_topac_lsp_eversource_presentation.pdf |2023, November 15: Eversource TOPAC (Transmission Owners Planning Advisory Committee presentation to PAC}}
  
-{{ ::w179_aot_application_structure_replacement_2-2-2023.pdf |2023, February 2AoT application}}+{{ ::w179:w-179_tca.pdf |2023, September 20: No significant effect on reliability for W-178 (3)}} 
 + 
 +{{ ::w-179_des_permit_with_waivers.pdf |2023, April 4DES permit with waivers of Env-Wq 1503.12(d)(1 & 2), Env-Wq 1503.21(d)(6 & 7) and Env-Wq 1504.09,}}
  
 {{ ::w179_des_-_fs_-_contractor_emails.pdf |2023, April 4: DES and Contractor emails}} {{ ::w179_des_-_fs_-_contractor_emails.pdf |2023, April 4: DES and Contractor emails}}
  
-{{ ::w179_nrcs_soil_report.pdf |NRCS soil report}}+{{ ::w179-project-plans-maps.pdf |2023, March 29; Environmental Resources Construction Map Set}}
  
-{{ ::w179_aot_extensive.pdf |AoT extensive}}+{{ ::w179_aot_extensive.pdf |20232, February 15 AoT application}} 
 + 
 +{{ ::w179_nrcs_soil_report.pdf |2023, February 7: 126 page NRCS soil report}}
  
 {{ ::attachment_rr-dpu-es-3.pdf |October 2022 PAC presentation, local system plan}} {{ ::attachment_rr-dpu-es-3.pdf |October 2022 PAC presentation, local system plan}}
Line 19: Line 25:
 {{ ::w179_structure_replacement_overview_updated_7-11-2022.pdf |2022, July 11, overview}} {{ ::w179_structure_replacement_overview_updated_7-11-2022.pdf |2022, July 11, overview}}
  
-{{ ::1-cre-2022-030-crossing_application.pdf |2022: petition}}+{{ ::22-049_2022-08-24_eversource_att-pet-approval-financing-transaction.pdf |2022, June 30: complete DE-22-049 document listing E$ proposed spending}} 
 + 
 +{{ ::1-cre-2022-030-crossing_application.pdf |2022, December 6: petition}}
  
 {{ ::2-cre-2022-030-exhibits_1-3.pdf |2022: exhibits}} {{ ::2-cre-2022-030-exhibits_1-3.pdf |2022: exhibits}}