345kV Line 326 {{ ::326_ras_retirement_project_i_3_9_letter_es_22_x01.pdf |2022, August 19: retirement of 326 line RAS E$ to ISO}} {{ :326:380_-_326_start_of_construction.pdf |2022, August 5: Start of construction notification}} {{ ::326:aot2196_rm.pdf |2022, July 29: DES permit waiving specific requirements of Env-Wq 1503.12(d)(1&2), Env-Wq 1503.21(d)(6&7), and Env-Wq 1504.09, }} {{ :326:380_-_326_eversource_failure_with_rare_species_protection.pdf |2022, July 18: "NHFG wants emphasize that this is an extremely sensitive area with rare animals known to make extensive use of the ROW and surrounding habitat, as well as an area of past compliance issues with Eversource."}} {{ :326:380_-_326_nhb_email.pdf |2022, June 20: New Hampshire Heritage Bureau email}} {{:a3_eversource_new_hampshire_asset_conditions_wood_structure_replacement.pdf|2022, June 15 presentation to PAC }} {{ :326:326_4-15-2022.pdf |2022, April 15: application to Town of Hudson for conditional use permit}} {{ :326:326_-2022-010-order-of-notice.pdf |2022, April 11: Order of Notice,line has three ACSR 850.8 Kcmil phase conductors, a single 7#8 Alumoweld static wire and a single 0646" OPGW wire will be transferred to the replacement structures.}} {{ :326:326_380_aot_permit_3-29-2022_.pdf |2022, March 29: AoT application, GZA}} {{ :326:326_380_ground_and_surface_water_aot_3-2022.pdf |2022, March ground and surface water AOT}} {{ :326:326_380_wetlands_damage_aot_3-2022.pdf |2022, March: disturbed areas AOT}} {{ ::1-cre-2022-010-petition.pdf |2022, March 29: petition for crossings}} {{ ::2-cre-2022-010-petition-attachments.pdf |2022, March 29: petition attachments}} {{ :326:326_3-17_2022_order.pdf |2022, March 17: Order re. petition for crossing rivers/public lands}} {{ ::3-cre-2022-010-energy-staff-recommendation.pdf |2022: staff recommendations}} {{ ::4-cre-2022-010-license.pdf |2022: license}} {{ ::326_345kv_line_diagram.pdf |line diagram}} {{ :326:326_.pdf |2021, May 4: Order, The Company proposes to replace existing Structure 5 with a newly constructed steel support structure. The three existing conductors and the existing static wire and optical ground wire (OPGW) on the line will be transferred to the new structure. The Company also seeks an after-the-fact license for the 2018 replacement of Structure 4 at the same crossing location}} {{ ::a9_eversource_345kv_structure_replacement_projects.pdf |2017, December presentation to PAC, replacement of 43 out of 166 poles.}} {{ ::k165_p145_.pdf |2016, January 7: TCA approval, apparently reliability}} {{ :326:326_proposed_reliability_upgrade_10-2012.png?linkonly |2012, October, proposed reliability upgrade}} {{ :psnh_cost_per_mile_115kv.jpg?linkonly |}}