391 345kV Line {{ :may_18_2023_e_pac_lines_map.png?linkonly |map showing line location}} {{ ::391:2023_05_18_meeting_minutes_final.pdf |2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "}} {{ ::a04_2023_05_28_pac_nh_wood_structure_and_opgw_installations.pdf |2023, May 18, presentation to PAC, replace 39 out of 335 structures; $12.4 million}} {{ :391:391_2023-03-07-eversource_to_des.pdf |2023, March 7: E$ to DES; "The gravel fill used within the CMP meets NHDOT 304.4 sieve size standards. For structures in uplands, the exterior of the CMP is padded with either 8” of flowable fill or 10” of NHDOT 304.4 mix. For structures in wetlands, we don’t put any material around the outside of the CMP"}} {{ :391:391_2023-02-28-field-inspection-2023224341.pdf |2023, February 8: DES inspection in response to complaint}} {{ :373:381_395_373_2022-02462_approval.pdf |2022, August 26: DES permit}} {{ :373:391_-_373_-_385_des_permit_with_waivers_2022.pdf |2022, August 19: DES permit with waivers}} {{ :391:391_2022-02462_pbn.pdf |2022, August 16: notification to DES; replacing 5 structures in Derry}} {{ :391:391_2022-02462_pbn.pdf |2022, August 16: notification to DES; replacing 5 structures in Derry}} {{ :373:375_-_383_-_391_f_g_and_es_discussion.pdf |2022, August 5: F&G and eversource discussion}} {{ :a3_eversource_new_hampshire_asset_conditions_wood_structure_replacement.pdf |2022, June 15 presentation to PAC, replace 27 out of 335 poles; $9. million for 391 line}} {{ :391:aot_2210_miscellaneous_r.pdf |2022, June 1; Alteration of Terrain application}} {{ :373:385-_373-_391_natural_heritage_bureau.pdf |2022, May 20: Natural Heritage Bureau}} {{ :391:aot-2210_plans.pdf |2022, May; Alteration of Terrain drawings,76 pages}} {{ :373:373_385_391_ground_and_surface_water_aot_5-2022.pdf |2022, May: ground and surface water overlay maps}} {{ :373:373_385_391_aot_4-2022.pdf |2022, April: Alteration of Terrain drawings, 48 pages}} {{ ::de-20-195-order-26-468.pdf |2021, April 7: order granting river crossing}} {{ :373:391_-_385_-_373_start_of_construction_form.pdf |2020, April 7: Start of construction notification}} {{ :373:385_-_391_-_373_dees_permit_with_waivers.pdf |2020, April 3: DES permit with waivers}} {{ :373:391_-_373_-_385_f_g.pdf |2020, April 2: F&G}} {{ :373:391_-_385_-_373_des_to_nhb.pdf |2020, March 17: DES to NHB}} {{ ::delineated_wetland_under_391.jpg?linkonly |delineated wetland under 391, "upgrade"}} {{ ::delineated_wetland_under_391_2_.jpg?linkonly |delineated wetland under 391, wetlands are not an asset, 'for' Eversource.}} {{ ::delineated_wetland_under_391_line.jpg?linkonly |delineated wetland under 391, "upgrade"}} {{ :391:aot1781_rm.pdf |2020, April 3; DES permission to Alter the Terrain, with waivers}} {{ :373:aot-1781_miscellaneous.pdf |2020, January 20: AoT application, 244 pages}} {{ :373:381_-_395_-_373_aot_application.pdf |2020: January 20: AoT application 254 pages}} {{ :373:373_385_391_surface_and_groundwater_1-20-2020.pdf |2020, January 1: ground and surface water overlay maps}} {{ :373:391_-_373_-_385_start_of_construction_form_2019.pdf |2019, July 1: Start of construction notification}} {{ ::391:aot1632_rm.pdf |2019, June 28; DES permission to Alter Terrain, with waivers, 391, 373, 385}} {{ :373:391_-_373_-_385_des_permit_with_waivers_6-22-2019.pdf |2019, June 22: DES permit with waivers}} {{ :391:aot-1632_miscellaneous_r.pdf |2019, May: Alteration of Terrain permit application}} {{ :385:391_2019-04-10_eversource_att_petition_cross_lamprey_river_deerfield.pdf |2019, April 10: exhibits for petition to cross Lamprey River, 2-7#8 Alumoweld}} {{ :385:391_2019-04-10_eversource_petition_cross_lamprey_river_deerfield.pdf |2019, April 10: petition to cross Lamprey River}} {{ :373:391_373_385_gsurface_and_groundwater_overlay_map_4-24-2019.pdf |2019, April 4: surface and groundwater overlay map}} {{ :391:aot-1632_plans.pdf |2019, April 2: Alteration of Terrain plans}} {{ :373:373_385_391_2018-00123_maintenance_notification.pdf |2018, October 28: installation of grounding rings at 30 structures, $10,000 paid to DES}} {{ ::a9_eversource_345kv_structure_replacement_projects.pdf |2017, December presentation to PAC, replacement of 69 out of 335 poles; $19.6 million}}