====== A-111 115kV transmission line ====== {{ ::e-115_z-1180_and_a-111_2023.pdf |2023, March 14: NEPOOL approval of $100 m.+ for A-111 , E-115 and Z-180 for Transmission Cost Allowance}} {{ ::e-115_z-1180_and_a-111_2023.pdf |2023, March: request to NEPOOL for TCA}} {{ ::new_hampton_sb_minutes_3-3-22.png?linkonly |March 3, 2022 New Hampton Selectboard minutes. E$ wants work to be allowed 7 days a week, 7:00 am to 7:00 pm. Dump trucks are delivering gravel for road building and there will be drilling.}} {{ ::a111:a111_start_of_construction_.pdf |2022: Start of Construction notice}} {{ ::license-granted.pdf |2022, January 21: DOE crossing permit; six crossings}} {{ ::crossing_license.pdf |2021, October 21: crossing license for nine structure replacement, reconductoring and OPGW, William H. Thomas State Forest and Pemigewasset River in Hill and Hampton}} {{ ::cr-2021-016-order-of-notice.pdf |2021, October 5: Order Nisi for crossing of William Thomas state forest and Pemigewasset River in Hill and New Hampton}} {{ ::a111:a111_des_permission_with_waiver_9-3-2021.pdf |2021, September 3: DES permit with waivers}} {{ :a111:a111_aot_with_lots_of_conditions.pdf |2021, August 21: AOT permitting plan. "Work pad restoration will begin following line construction completion. Work pads will be covered with topsoil, seeded, and mulched."}} {{ ::a05_1_es-21-tca-44_final.pdf |2021, August 19, Application to NEPOOL for TCA. $33. m. Rebuilding line at the same size is not presented as an alternative. No pole inspections submitted. Described as reliability and asset condition project}} {{ ::a111-project-construction-factsheet.pdf |2021, July: Project construction fact sheet citing reliability}} {{ ::iso_7-15-2021_no_significant_impact_of_interconnection.pdf |2021, July 15: ISO determination of no problems with interconnection}} {{ ::staff_recommend.pdf |2021, June 25: staff recommendation; nine wood structures replaced with steel, existing conductors will be replaced with (3) new ACSS 1272 54/19 kcmil conductors. Two existing shield wires will be replaced with (2) 48 fiber optical ground wire (OPGW) }} {{ :a111:a-111_2021-06-25_staff_rec.pdf |2021, June 21: staff recommendation}} {{ :a111:a-111_2021-06-02_eversource_petition_crossing.pdf |2021, June 6: petition for crossing the Pemigewasset River in Hill and New Hampton, and William H.Thomas State Forest: "The proposed project for the A111 encompasses a full line rebuild."}} {{ :a111:a-111_2021-06-02_eversource_att_petition_crossing.pdf |2021, June 2: petition for crossing; exhibits: two 48 fiber .646 OPGW, steel structures, 1272 ACSS 54/7 conductor}} {{ :a111:a-111_des_permit.pdf |2021, May 26: AoT application and DES permit with waivers}} {{ ::a111:a111_nhb_report.pdf |2021, May 19: NHB report}} {{ ::a111_full_rebuild_.pdf |2021, April 8: Submission to SEC claiming new, larger, taller, steel line is a one-for-one replacement}} {{ :a111:a-111_1537_2021-0906.pdf |2021, March 9: inspection permit DES}} {{ :a111:a-111_2020-11-12_order_26423.pdf |2020, November 12: license for crossing}} {{ :a111:a-111_2020-10-22_staff_rec_rev.pdf |2020, October 22, revised staff recommendation; '“This crossing was previously licensed by the PUC pursuant to Order 12,219 in Docket # DE 76-22 issued March 12, 1976.” should have read “This crossing was previously licensed by the PUC pursuant to Order 12,219 in Docket # DE 76-22 issued April 21, 1976."}} {{ :a111:a-111_2020-10-16_eversource_supp_petition.pdf |2020, October 16: supplemental petition with 1976 crossing date corrected}} {{ :a111:a-111_2020-09-04_staff_rec.pdf |2020, September 4: staff recommendation; ES’s existing A111 line is not being relocated as result of this project using the existing conductors. The existing wood structure # 79 is being replaced with (3) steel pole structures due to age and environmental damage.}} {{ :a111:a-111_2020-03-31_eversource_petition_crossing.pdf |2020, March 31: petition to cross Pemigewasset River in Hill and New Hampton, red cedar structure 79 requires immediate replacement, steel, no conductor or ground wire changes}} {{ :a111:a-111_2020-03-31_eversource_att_petition_crossing.pdf |2020, March 31: Pemigewasset River crossing petition exhibits, 336.4 ASCR 26/7, 7#8 alumoweld static lines, 85' and 95' structures, 37.4' clearance}} {{ ::a5_webster_beebe_river_115kv_corridor_asset-conditions_and_opgw_project_lines_a111_e115_z180_rev1_clean.pdf |December 2020 Asset Condition PAC presentation}} {{ ::de-20-042.pdf |November 2020, petition for amended license}} {{ ::e-115_and_a-111_2-15.png?linkonly |2015: "The load and added local generation in this area has not required the upgrading of either line."}}