U-199 115kV line {{ ::u199-permitting-plans.pdf |2023, October 10: DRAFT permitting plans}} {{ ::2023_05_18_meeting_minutes_final.pdf |2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026}} {{ :e194:e194_u181_alteration_of_terrain_permit_-_final_as_submitted.pdf |2023, May: Alteration of Terrain application}} {{ ::b112-u199-q195_rebuild_presentation.pdf |2023, May 18, presentation to PAC}} {{ ::22-049_2022-08-24_eversource_att-pet-approval-financing-transaction.pdf |2022, June 30: complete DE-22-049 document listing E$ proposed spending}} {{ ::u199:u-199_2014_a_mile_line_rebuild_and_river_crossing.pdf |2014, December 18:PSNH letter to PUC re changes in crossing}} {{ ::u199:u-199_2015_revised_crossing.pdf |2015, April 13: Order Nisi, Ammonoosuc River}} {{ ::u199:u-199_crossing_ammonoosuc_2014.pdf |2014: exhibits for crossing Ammonoosuc River}}