D-121 115kV line

map showing line location

2023, June 14: structure structure will be replaced with a weathering steel equivalent, the existing three conductors, and two OPGW wires will be unchanged

2023, June 14:crossing exhibits; 795 ASCR 36/1 Coot, 48 fiber .646 AFL S3-81/69/646 OPGW

2023, June 14: AoT checklist

2023, May 14: DES permit waiving specific requirements of Env-Wq 1503.12(d)(1 & 2), Env-Wq 1503.21(d)(6 & 7), and Env-Wq 1504.09,

2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "

2023, May 18, presentation to PAC, replace 18 out of 154 structures; $5. million

2023, May 14: DES permit with waivers

2023, March 28: Alteration of Terrain application

2023, March 23: Water Resources maps

2022, August 3: Goldenrod

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2021, December 9: Town of Bow, Conditional Use Permit and public hearing on wetlands damage and after-the-fact truck access

2021, September 28: prehearing order

2021, August 18: AoT cover sheet

2021, August 18: DES permit waiving specific requirements of Env-Wq 1504.09,

2021, August 18: Surface and Groundwater maps

2021, August petition

2021, June 16: presentation to PAC

2021, May 18: Wildlife assessment

2021, May 17: Original AoT application

2021, May: Wildlife assessment