G-192 115kV Line
2022, October 19: presentation to PAC
2021, September 21: ISO identifies no impacts to system reliability from project
2021, September 23; PUC grants permit to cross public lands/waters
2021, April 29: staff recommendation
2021, March 24: exhibits, also dated 2016