J-114

map showing line location

2023, June 27: Alteration of Terrain stamped first page

2023, June 20: Piscataquog Local Advisory Committee meeting agenda

2023, June 21: DES permit waiving specific requirements of Env-Wq 1503.12(d)(1 & 2), Env-Wq 1503.21(d)(6 & 7), and Env-Wq 1504.09,

2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "

2023, May 18, presentation to PAC, replace 32 out of 49 structures and reconductor with Optical Ground Wire (OPGW); $9.7 million

2023, May 16th, PRLAC June Agenda

2023, May 9: AoT checklist

2023, April 5: Environmental Resources map, GZA

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2023, February 24: license to cross

2023, February 22: staff recommendation; the existing static wire will be replaced with a new OPGW wire and the installation of a second OPGW wire. The existing phase conductors will remain unchanged.

2023, February 16: petition for crossing Piscataqua River and State lands; structure replacement and optical ground wire replacement and addition of a second optical ground wire

2022, November 4: crossing exhibits; 48 fiber.646 OPGW, 144 fiber .646 OPGW, 795 ASCR 36/1 Coot

2012, October, proposed reliability upgrade