2023, October:RSP asset condition list
2023, June 15 PAC minutes
2023, June 15, PAC presentation
2023, November 6: crossing application; "In addition to the structure replacements and the Greggs substation expansion, the existing pole top static wire is being removed and replaced with an OPGW wire “48F ᴓ 0.646” AFL DNO-11852”. The three existing conductors and the second existing OPGW wire at the crossing spans shall remain unchanged in the course of the structure replacements."
2023: crossing exhibits; 1590 ASCR 45/7 Lapwing,48 fiber .646 AFL OPGW, 84 fiber OPGW
1976: Order, Piscataqua River crossing
1976: reconstructing line