J-114
2023, May 9: AoT checklist
j114_des_permit_with_waivers.pdf
j114_piscataquog_lac.pdf
2023, April 5: Environmental Resources map
2023, April 5: Approval of
j114_piscataquog_lac.pdf
DES permits Alteration of Terrain with waivers
Alteration of Terrain Plans
Alteration of Terrain stamped first page
2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "
2023, May 18, presentation to PAC, replace 32 out of 49 structures and reconductor with Optical Ground Wire (OPGW); $9.7 million
2023, May 16th, PRLAC June Agenda