Q-195 115kV line

2024, December 5: Eversource Petition to rebuild Q-195 in Concord and Waterford, Vermont

2024, December 5: PSNH certifies it has complied with the advance notification to abutters requirements of the Vermont PUC

2024, December: List of adjoining landowners, Vermont

2025, December 5: Eversource applies to Vermont PUC for a certificate of Public Good

2025, December: Eversource pays Vermont $100,000. Application fee for Certificate of Public Good

2023, November 29: structure specs, Vermont

2024, November 14: Project map, Vermont

2024, November 14: PREFILED TESTIMONY OF SAMUEL HARRIS ON BEHALF OF Eversource, Vermont

2024, November 1: Aesthetic and Orderly Development Analysis Report, Vermont

2024, November 1: Prefiled testimony by Ryan Scott for Eversource, Vermont

2024, October 28: Historic and Archaeological Resources Report for Concord and Waterford, Vermont

2024, September: Project location map, Vermont

Vermont PUC docket for Q-195 in Concord and Waterford

2024, September 8 (found on the site): Vermont project mapping

2023 May 18 PAC minutes, Replace 224 wood structures with 223 new steel structures, Re-conductor 17.5 miles of 336/477/795 ACSR with 1272 ACSS, Install 35 miles of OPGW (2 x 17.5 mi, Estimated PTF Cost: $100.00M (-25% / +50%), Projected In-service Date: Q4, 2026

2023, May 18 presentation to PAC

2023, February 28: "Dear Neighbor" letter

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2017 river crossing poles fine

2017, December 14: assertion of 2015 assertion of crossing rights