U-181 115kV line
2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "
2023, May 18, presentation to PAC, replace 24 out of 67 structures; $8.5 million
2023: may 18 PAC meeting minutes
2023, June 15 Portsmouth wetlands permit
2023, June 5:Asset Condition projects called Maintenance Projects
2023, March 10: Alteration of Terrain application "The total land disturbance for the project was calculated to be approximately 61.1 acres. The disturbance area includes the work pads, access roads, and the estimated limits of necessary grading."