K-105 115kV line built in 2002 | ====== K-105 115kV line ====== |
| |
| |
| built in 2002, Greggs to North Merrimack |
| |
{{ :may_18_2023_e_pac_lines_map.png?linkonly |map showing line location}} | {{ :may_18_2023_e_pac_lines_map.png?linkonly |map showing line location}} |
{{ :k105:k-105_2021-08-12_eversource_replacement_petition.pdf |2021, August 12: petition for crossing Everett Turnpike}} | {{ :k105:k-105_2021-08-12_eversource_replacement_petition.pdf |2021, August 12: petition for crossing Everett Turnpike}} |
| |
{{ :k105:k-105_2021-08-12_eversource_att_replacement_petition.pdf |2021, August 12: petition exhibits}} | {{ :k105:k-105_2021-08-12_eversource_att_replacement_petition.pdf |2021, August 12: petition exhibits; 1272 ASCR 45/7 and 72 fiber OPGW}} |
| |
{{ :k105:k-105_2021-04-28_staff_rec.pdf |2021, April 28: staff recommendation}} | {{ :k105:k-105_2021-04-28_staff_rec.pdf |2021, April 28: staff recommendation}} |
| |
{{ ::staff_recommendation_k-105.pdf |staff recommendations}} | |
| |
{{ :k105:k-105_2021-03-31_eversource_crossing.pdf |2021, March 31: crossing petition}} | {{ :k105:k-105_2021-03-31_eversource_crossing.pdf |2021, March 31: crossing petition}} |