User Tools

Site Tools


asset_conditions_documents

Asset Condition documents

Asset Condition Lists

2024, April 8: kp comments on Small Projects Day application

2024, April 6: comments on FirstLight Eversource fiber optic third party contractor document of 3/31/2021

2024, April 3: WMNF Small Projects Day application from E$ for construction in North Woodstock

2024, April 2: PAC notice of corrections to 3/2024 RSP list

2024, April 2: PAC response to stakeholder comments of 3/2024

2024, March 20: Maine PUC comments to PAC on Eversource X-178 presentation

2024, March 15: NESCOE comments to PAC on Eversource X-178 presentation

2024, February 27: PAC "Guidelines" for public comments

2024, February 12: PUC denies motion for reconsideration, DE-23-056 "Commission concluded it had the authority to conduct a fact- finding inquiry into Eversource’s asset condition projects to the extent they affect New Hampshire ratepayers....Given the broad scope of review the Petitioner sought, the Commission declined to initiate an investigation based on the Petition.

2024, February 2: Utility Dive; "Eversource, others may be capitalizing on lax reviews for some transmission projects: Maine officials"

2024, February 1: "MOTION FOR LEAVE TO ANSWER AND ANSWER OF THE ELECTRICITY TRANSMISSION COMPETITION COALITION TO THE UNAUTHORIZED SUPPLEMENTAL REPLY COMMENTS OF CERTAIN ANTI-COMPETITION INCUMBENT UTILITIES"

2024, January 28: k. pastoriza comment #2 on Hurd State Park project

2024, January 25: New England Transmission operators asset database

2024, January 21: k. pastoriza comment on Hurd State Park presentation and other problems

2024, January 19: Eversource objection to motion for reconsideration

2024, January 18" Economic study presentation

2024, January 18: overview economic study

2024, January 18: Eversource presentation to PAC; Hurd State Park project

2024, January 11: motion for PUC reconsideration of denial

2024, January 11: supplement to motion.

2024, January 8 Peskoe comment to FERC

2024, January 5: NH PUC denial of request to investigate Eversource asset condition projects

2023, October 20, Sugar Hill support of PUC investigation of Eversource asset condition projects

2023, December 15: k. pastoriza comments and questions on ES presentation on A-152 and M-127 projects

December 14, 2023: k. pastoriza response to NETO 11/15/2023 response to stakeholder comments

a05_2023_11_15_asset_condition_project_forecast.pdf

December 20, 2023: ES presentation on A-152 and M-127 structure replacements

December 20, 2023: NETO update on Asset Condition project process 'enhancements'

2023, November 15: NETO responses to stakeholder requests for improvement of Asset Condition project presentations

2023, November 15: Transmission corporation authored guidelines for asset condition presentations

2023, November 15: Eversource TOPAC (Transmission Owners Planning Advisory Committee) presentation to PAC

2023, October 18: NETO (New England Transmission Operators) asset management 'improvement' process presentation

2023, September 15: Massachusetts Attorney General’s Office Feedback Regarding the New England Transmission Owners August 8, 2023, Letter and Proposed Guidelines for Asset Condition Project Presentations

2023, September 15: COMMENTS BY SYNAPSE ON DRAFT GUIDELINES FOR CREATION OF ASSET CONDITION PROJECT PRESENTATIONS

a03_2023_09_20_pac_ptf_asset_condition_database_presentation.pdf

2023, September 14: Consumer Advocates of New England letter to PAC re. Asset Condition problem

2023, September 7:questions for Eversource upcoming X-178 so-called asset condition project, presentation to the PAC

2023, August 19: k. pastoriza comment on draft PAC presentation outline.

2023, August 18: Office of the Consumer Advocate reply Brief DE-23-056

2023, August 16: k. pastoriza comments to PAC

2023, July 14: NESCOE Asset Condition Request to NETOs

2023, June 30 NESCOE request to Eversource for more information on a non-Asset-Condition project.

2023, March: Asset Condition map

2023, June: Asset Condition map

2023, March: Eversource asset condition projects NH pdf

"The rebuild of the X178 line did not require the acquisition of additional ROW as it was placed off center within the existing ROW, leaving space for future use of the ROW. The load in this area [and others] has not required the upgrade of the remaining sections of the X178 [and other lines]."

2023, June, final project list presentation

2023, May: Synapse asset condition letter

May 2023 asset condition presentation

2023, February 8: NESCOE asset condition letter

2022, March: final project list presentation

2021, June: ISO regional planning needs and solutions

2019: What the PUC said about Asset Condition projects

Decrepit (?) Eversource poles left by bus stop

2023 line map, Deerfield area

SegTel and Eversource fiber optic case

Techno-economic comparisons of hvac and simultaneous AC-DC transmission

Condemnation deed, X-178, Easton. Reasonable need, no 'intelligence' rights

Typical X-178 ROW deed, no transmission of 'intelligence' permitted.

New 115V tower, partial image, no dimensions

acknowledgement of petition

petition for review of eversource asset condition projects

supplement to petition

2017, December 20: Asset Condition project presentation thresholds

asset_conditions_documents.txt · Last modified: 2024/04/28 04:30 by sigridundset

Donate Powered by PHP Valid HTML5 Valid CSS Driven by DokuWiki