-Basic project plansheets and structure height changes removed from Eversource "site" some time around mid-April, 2025+===== Basic project plansheets and structure height changes removed from Eversource "site" some time around mid-April, 2025 ===== 
  
 {{ :x178:project_information_form_-_reel_brook_trail_kinsman_ridge_trail_relocations.pdf |2025, April: Re-routing of Reel Brook Trail, apparently around the existing trail which Eversource plans to turn into a road with two cross-roads, to access the X-178}} {{ :x178:project_information_form_-_reel_brook_trail_kinsman_ridge_trail_relocations.pdf |2025, April: Re-routing of Reel Brook Trail, apparently around the existing trail which Eversource plans to turn into a road with two cross-roads, to access the X-178}}
Line 15: Line 16:
 {{ :x178:2024-12-23_kp_comment_on_eversource_waivers_from_permit_requirements.pdf |December 23: Eversource waivers from DES permit requirements}} {{ :x178:2024-12-23_kp_comment_on_eversource_waivers_from_permit_requirements.pdf |December 23: Eversource waivers from DES permit requirements}}
  
-{{ :x178:x-178_boring_plan.pdf |2025, January 20: Statutory Permit by Notification for geotechnical borings of unstated depth on the X-178 easement in White Mountain National Forest."Threats to both the medium level fen system and poor level fen/bog system include changes to hydrology, especially those that result in pooling, increased nutrient input and increased sedimentation."}}+{{ :x178:x-178_boring_plan.pdf |2025, January 20: Statutory Permit by Notification for geotechnical borings of unstated depth on the X-178 easement in White Mountain National Forest."Threats to both the medium level fen system and poor level fen/bog system include changes to hydrology, especially those that result in pooling, increased nutrient input and increased sedimentation." Borings postponed to Q1, 2026}}
  
 {{ :x178:easton_variance_application_11-12-24_opt.pdf |2025, January 7: Eversource application for a variance from Easton's structure height restriction.}} {{ :x178:easton_variance_application_11-12-24_opt.pdf |2025, January 7: Eversource application for a variance from Easton's structure height restriction.}}