Both sides previous revisionPrevious revisionNext revision | Previous revision |
s-136 [2024/04/28 08:01] – sigridundset | s-136 [2024/11/22 08:08] (current) – sigridundset |
---|
====== S-136 115kV line ====== | ====== S-136 115kV line ====== |
| |
| {{ ::eversource_2024_lsp_a.pdf |2024, November 20: Local System Plan, under-construction}} |
| |
| {{ :s136:eversource_fs_application_for_s-136_line_rebuild.pdf |2024, October 14: kp comment on Eversource application to Forest Service}} |
| |
| {{ :s136:project_information_form_-_eversource_s136_transmission_line_rebuild.pdf |2024, October 4: Eversource small projects day application for replacement of 214 structures and permanent road and crane pad construction in White Mountain National Forest}} |
| |
{{ :s136:s-136_-2023-027-application.pdf |2023, December 19: petition to cross}} | {{ :s136:s-136_-2023-027-application.pdf |2023, December 19: petition to cross}} |
{{ ::s136_des_permit_with_waivers_4-9-2020.pdf |2020, April 9: DES permit waiving | {{ ::s136_des_permit_with_waivers_4-9-2020.pdf |2020, April 9: DES permit waiving |
specific requirements of: Env-Wq 1504.09, }} | specific requirements of: Env-Wq 1504.09, }} |
| |
| {{ :s136:s-136_1_aot_area.png?linkonly |2020, April 9: 20.1 acres impacts}} |
| |
{{ :s136:19-162_2020-04-01_eversource_supp_petition_crossing.pdf |2020, April 1: crossing petition supplement, " Eversource intends to complete four structure replacements...(Str. 293, 294 and 298, 299)... in addition to replacing the existing static wire with OPGW"}} | {{ :s136:19-162_2020-04-01_eversource_supp_petition_crossing.pdf |2020, April 1: crossing petition supplement, " Eversource intends to complete four structure replacements...(Str. 293, 294 and 298, 299)... in addition to replacing the existing static wire with OPGW"}} |