Geotechnical boring White Mountain National Forest

2025, March 18: "we were forced to postpone the geotechnical investigation to Q1 of 2026"

2025, February 15: Expired $82. permit from WMNF to Eversource for geotechnical borings in WMNF

2025, February 12: emails re permit

2025, February 12: emails re extending end date for permit.

2025, February 11: WMNF emails re effect of boring on animals. Frak-out of drilling fluids into Bog Pond or local steams not considered.

2025, January 31: FS has no problem with boring which it assumes will stay within the easement.

2025, January 28: Archaeological questions. "we [Forest Service] would have most likely not agreed that Gordon Pond was a historic trail (all our trails could be considered historic)"

2025, January 23: Boring and wildlife.

2025, January 15: geotech questions

2025, January 14: Eversource to WMNF boring plan. No mention of frak-out of drilling fluids to local streams as happened during Northern Pass.

2025, January 9: email question on geotechnical borings

2025, January 1: Small Projects Day application for geotechnical borings. No public involvement.

2022-2023: Planned boring location photographs and 12/23/24 Crux boring plans with only basic details. No frak-out plans.

2024, August 26: Flight plans for boring reconnaissance

2024, August 14: Presentation to WMNF on helicopter access plans and micropile foundations

2024, March 22: Boring plans/maps