2024, April 10: Eversource request to Franklin for variance from 50' height limit for transmission structures:
2023, November 15: Eversource TOPAC (Transmission Owners Planning Advisory Committee presentation to PAC
2023, June 15: "Dear Neighbor" Letter
2021, order of notice
2021, June 21: staff recommendation
2021, May 6: petition for crossing Lake Winnisquam; 795 ASCR 26/7 Drake conductors, one static line and one OPGW remain the same. Brugg 571 12 fiber OPGW, 7#8 Alumoweld,
2021, May 6: petition for crossing exhibit and older exhibits with (2) 7#8 Alumoweld and 796 ASCR 26/7 Drake
2004, January 39: Order Nisi; crossings of Pemigewasset River in the City of Franklin, the Winnipesaukee River in the Towns of Tilton and Belmont, and Lake Winnisquam in the Town of Belmont, New Hampshire.
2002: petition for crossing four water bodies below
4/21/1976: Order for crossing of Pemigewasset River, DE 76-22 (Order No. 12,219)
8/4/1975: Order for crossing of Ephraim’s Cove, DE 75-149 (Order No. 11,949)
6/16/1976: order for crossing of Winnisquam (Ephraim’s Bay) and Winnepesaukee, DE 75-156 (order 11,949)
8/31/1955: crossing of Lake Winnisquam, Docket D-E3442 (Order No. 6,668,)
5/23/1938: license from B&M Railroad under a pole and wire agreement, for rail-bed crossing in Tilton