K-105 115kV line built in 2002
2022, June 30: complete DE-22-049 document listing E$ proposed spending
December 2019, 2020-2023 revisions PAC presentation, replace 32 structures
2021, October 8: license for crossing
2021, March 7: presentation to PAC; 10.8 miles, replace 112 structures $14.7 m.