U-181 115kV line
2023, May 18 PAC minutes "A stakeholder suggested the ISO could take an “if you build it, they will come approach” but another stakeholder raised concern that this could be “building a bridge to nowhere.” "
2023, May 18, presentation to PAC, replace 24 out of 67 structures; $8.5 million
2023, May: Alteration of Terrain application
2023, August 7: email re alteration of terrain permit application
2023, July 29: DES permit with waivers
2023, June 15, Portsmouth wetlands permit