P-145 115kV line
2023, July 7: $51 m. Transmission Cost Allocation approved
2023, May 16: NEPOOL Reliability meeting agenda
2022, October 18: Rare plants email
2022, October 3: Fish and Game email
2022, September 17: Amended AOT application
2022, September 8: Alteration of Terrain application
2022, August 15: Start of construction notification
2022, August 12 permitting maps set
2022, July: construction "fact" sheet
2022, June 30: complete DE-22-049 document listing E$ proposed spending
2022, April 27: AOT cover letter
2022, April 25: AOT application
2022, March 25: crossing license
2022, March 14: Eversource presentation to Concord City Council
2022, February 28: staff recommendation
2022, after February 15: order of notice
2022, February 15: petition to DOE for crossings
2022, February 8: Draft project map
2021, December 13: petition attachments showing profiles, also dated 12/2016
2016, January 7: TCA approval, apparently reliability