U-199 115kV line

2025-5-9: Bethlehem re-appears in PUC docket

2025, March: U-199 cost increases from $51 m. to $71 m.

2025, April 5: construction mesas with rip-rap slopes

2025, April 1: Bethlehem legal counsel withdrawal from docket.

2025, March 31: Eversource request to withdraw X-178 from docket.

2025, February 2: Comment to PUC on two months of inactivity on the docket while the U-199 construction is moving toward Bethlehem.

2025, January 8: matting

2025, January 8: construction

2024, December 21: construction

2024, August 6: crossing license

2024: structure heights, Littleton, withheld for months by Eversource

2024, February 14: no adverse effects to system from U-199 rebuild

2023, May 18: PAC meeting minutes

2024, May: Structure heights existing and proposed, Bethlehem, withheld for months by Eversource

2024, May 16: Project Introduction "Fact Sheet."

2023, October 18: "Dear Neighbor" letter

2023, October 10: DRAFT permitting plans

2023 May 18 PAC minutes, Replace 104 wood and 1 steel structures with new steel structures, Re-conductor 9.75 miles of 795ACSR with 1272 ACSS, Install 19.5 miles of OPGW (2 x 9.75 mi), Estimated PTF Cost: $51.18M (-25% / +50%), Projected In-service Date: Q2, 2026

2023, May 18, presentation to PAC

2023, February 10: "Dear Neighbor" letter

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2014, December 18:PSNH letter to PUC re changes in crossing

2015, April 13: Order Nisi, Ammonoosuc River

2014: exhibits for crossing Ammonoosuc River, steel structures, conductor remains 795