====== U-199 115kV line ====== | ====== U-199 115kV line ====== |
| |
| |
| {{ :u199:24-087-2025-07-24-nhpuc-proc-order-re-mot-for-summary-resolution-of-proceeding.pdf |2025, July 24: PUC denies Eversource motion for summary waiver.}} |
| |
| {{ :u199:u-199_2025_and_2022.png?linkonly |2025, June: Google Earth U-199 2025 and 2022}} |
| |
| {{ :u199:24-087-2025-07-22-eversource-motion-summary-resolution-proceeding.pdf |2025, July 22: Eversource motion for summary waiver of Bethlehem's zoning.}} |
| |
| {{ :u199:doe_witness_contradicts_eversource_23-087_1.pdf |2025, June: DOE witness DeVergilio contradicts Eversource testimony}} |
| |
{{ :u199:24-087-2025-06-06-nhdoe-testimony-devirgilio-1.pdf |2025, June 6: DOE witness DeVergilio testimony in support of Eversource with no evidence presented.}} | {{ :u199:24-087-2025-06-06-nhdoe-testimony-devirgilio-1.pdf |2025, June 6: DOE witness DeVergilio testimony in support of Eversource with no evidence presented.}} |
| |
{{ :u199:24-087-2025-06-06-nhdoe-position-statement.pdf |2025, June 6: After pretending to oppose Eversource and support Bethlehem, NH DOE shows its true position as a captured agency}} | {{ :u199:24-087-2025-06-06-nhdoe-position-statement.pdf |2025, June 6: After pretending to oppose Eversource and support Bethlehem, NH DOE acts as a captured agency}} |
| |
{{ :u199:24-087-2025-06-06-nhdoe-att-testimony-devirgilio.pdf |2025, June 6: DeVergilio resume and more responses to questions.}} | {{ :u199:24-087-2025-06-06-nhdoe-att-testimony-devirgilio.pdf |2025, June 6: DeVergilio resume and more responses to questions.}} |