2023, November 15: Eversource TOPAC (Transmission Owners Planning Advisory Committee presentation to PAC

2023, September 20: DES acknowledges Eversource withdrawal of wetlands application

2022, October 19: 2019 local system plan E$-presentation to PAC

2022, September 27: Project plan revision

2022, August 25: Dear Neighbor letter

2022, July 21: Start of construction notification

2022, July 15: Environmental Resources AOT

2021, July 15: ISO has no problems with interconnection

2022, June: Construction "fact" sheet

2022, June: project "fact" sheet

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2022, April 8: USFS response to FOIA

2022: restoration plan

WMNF plan set

2022,January 19: order of notice

route_110_aerial_before.png

route_110_stark_south_before.png

route_110_before.png

WMNF specialist review form

2021, January 3; E$ petition for crossing

2021 petition attachments showing structures exceeding required clearance by 6'-18'

2019, October 24: PAC local system plan, E$ presentation to PAC

heading_to_lost_nation_groveton.jpg

intersection_of_0_154_with_christine_lake_rd..jpg

intersection_of_o154_with_christine_lake_rd._2.jpg

o154_either_side_of_route_110.jpg

o154_either_side_of_route_110_2_northumberland.jpg

stark_3.jpg

stark_4.jpg

stark_5.jpg

stark_6.jpg

stark_7.jpg

O-154 before "upgrade"