V-191 115kV line, built in 2005

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2022, June 2: AoT stamped page

2022, June 22: DES permit waiving specific requirements of Env-Wq 1503.12(d), Env-Wq 1503.21(d)(6) and (7), and Env-Wq 1504.09,

2022, June 21: Environmental Resources map

2022, June 17: DES, Fish & Game and contractor emails

2022, May 16: Fish & Game recommendations, email

2022, April: AoT application

2022, January 3: DOE order permitting crossing

2021, October 21: staff recommendation

2021, October 20: Revised presentation to PAC

2021, after October: DOE order of hearing on crossing petition

2021, October 20; PAC presentation, replace 41 out of 60 structures at $11 m.

2021, October 15: E$ crossing petition

2021, May 7: exhibits for crossing petition, also dated December 2016