K-105 115kV line built in 2002
2022, June 30: complete DE-22-049 document listing E$ proposed spending
2021, October 7, staff recommendation
2021, August 12: replacement petition
2021, April 28: staff recommendation
2021, March 31: crossing petition
2021, March 7: presentation to PAC; 10.8 miles, replace 112 structures $14.7 m.
December 2019, 2020-2023 revisions PAC presentation, replace 32 structures