M-183 115kV line
map
2023, March 30: start of construction form
2023, March 30: DES permit waiving specific requirements of Env-Wq 1503.21(c)(2) and Env-Wq 1504.09,
2023, March 29: Alteration of Terrain application
2023, March 29: Environmental Resources map
2023, March 29: transmittal of final documents. "Additionally, project construction is planned to begin as soon as possible upon permit approval. With that, I wanted to inquire about the start of construction waiver and how/when that should be
submitted?'
2023, March 16: PAC minutes; no comment from PAC on project
2023, March 16: PAC presentation
2023, February 14: "Although the Committee reviewed the project and plans and determined the minimal impact on the Cocheco River corridor would occur, it was noted that the project appeared to be outside the
jurisdiction of the committee"
2023, February 16: email E$, Fish & Game, DES