367 345kV
2022, August 24: F&G and eversource emails re Blanding's turtle
2022, August 19: DES permit with waivers
2021, June 30: license for crossings
2022, May: surface and groundwater overlay plans
2020, October 16: license for crossing
2020, July 14 permission from DES to alter terrain
2020, July 14: DES permit with waiver
2020, May 13: AOT application with note from DES re threatened species
2020, April 7: Start of construction notification
2020, April 3: DES permit with waivers
2019, July 1: Start of construction notification
2019, June 28: DES permit with waivers
2019, May: original AOT application
2019, May 1: DES permit with waiver
2019, April 24: surface and groundwater overlay plans
2017, December presentation to PAC, replacement of 56 out of 281 poles.