385 345kV Line

map showing line location

2022, August 26: DES permit

2022, August 19: DES permit with waivers

2022, August 16: notification to DES; replacing 5 structures in Derry

2022, August 5: F&G and eversource discussion- too bad for Blanding's turtle.

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2022, June 15 report to PAC, replace 25 out of 169 structures; $8.6 m

2022, April Alteration of Terrain plans

2021, April 7,order granting river crossing

2022, May 20: Natural Heritage Bureau

2022, May: ground and surface water overlay maps

2020, September 2: Order re crossing, no info. on lines

2020, September 2: petition to cross

2020, May 4: crossing petition; No conductor, shield wire or neutral shall be added or replaced as part of those structure replacements; instead, existing conductors and wires shall be tran sferred to the new structures. Sougehan River

2020, April 7: Start of construction notification

2020, April 3: DES permit with waivers

2020, April 2: F&G

2020, March 17: DES to NHB

2020, January 20: AoT application, 244 pages

2020: January 20: AoT application 254 pages

2020, January 20: ground and surface water overlay maps

2019, July 1: Start of construction notification

2019, June 22: DES permit with waivers

2019, May: AOT application

2019, April 4: surface and groundwater overlay map

2019, July 1: start of construction notice

2019, June 28: DES permit with waivers

2019, May: AOT permit application

2019, April 24: surface and groundwater overlay

2018, October 28: installation of grounding rings at 30 structures, $10,000 paid to DES