H-123 115kV line

line map

2023 line map

2023: license to cross

2023, March 16: PAC minutes; no comment from PAC on project

2023, March 12: PAC minutes

2023, March 16: PAC presentation, replace 7 remaining wood structures with steel

2023, January 26: license for crossing

2023 staff recommendation

2023, January 18: E$ petition for crossing public lands/waters; The proposed project for the H123 encompasses a static wire to optical ground wire replacement project.

2022, November 19:petition exhibits also dated 2016

2022, May: Application for Special Exception Litchfield

2022, May 23; license for crossing

2022 staff recommendation; "The H123’s existing three phase conductors, a single OPGW wire, and a single static wire between Structures 201 and 202, whose specifications were identified on Exhibit 2 submitted by ES, will remain unchanged in the course of relocation to the replacement steel structures."

2022, May 2: E$ petition to cross public waters/lands

2022 petition attachments

2019, February 9; E$ petition for crossing Merrimack River; Shield Wire: 7#8 Alumoweld, Transmission Wire: 795 kcmil ACSR 36/1, ADSS Wire: ADSS 72 Fiber

2019, January 11: exhibits for petition

2018, December; EPA reports

2018, October 17; presentation to PAC, replace 29 structures at $6. million

2016, January 7: TCA approval, apparently reliability

2012, March 6: staff recommendation; to alter an existing crossing of the Merrimack River in Merrimack and Litchfield, New Hampshire by altering the material, height, location of both support structures as well as increasing the conductor size and material, increasing the size and material of the static wire which serves as a shield wire and replacing the communication wire from an ADSS type to an OPGW line (84 fiber optic cable). The relocation of the existing support structures of an existing 115 kv transmission line (Circuit K- 165 referred to as the “Busch Tap”) on both sides of the Merrimack River allows for proper clearance from a newly proposed circuit H- 123 (115 kV) that will be installed between Line 380 (345kV) and the relocated K-165 (115 kV)

2011, November 30: crossing exhibits