M-183 115kV line
map
2023, March 30: start of construction form
2023, March 30: DES permit waiving specific requirements of Env-Wq 1503.21(c)(2) and Env-Wq 1504.09,
2023, March 29: Alteration of Terrain application
2023, March 29: Environmental Resources map
2023, March 29: transmittal of final documents. "Additionally, project construction is planned to begin as soon as possible upon permit approval. With that, I wanted to inquire about the start of construction waiver and how/when that should be
submitted?'
2023, March 16: PAC minutes; no comment from PAC on project
2023, March 16: PAC presentation
2023, February 14: "Although the Committee reviewed the project and plans and determined the minimal impact on the Cocheco River corridor would occur, it was noted that the project appeared to be outside the jurisdiction of the committee"
2023, February 16: email E$, Fish & Game, DES
2023, February 7: crossing license with revision and original license. "The proposed project encompasses a structure replacement whereby Structure 88 at the public water and Structures 81 through 85 at the state-owned land crossing span are to be replaced with a weathering steel equivalent having the design and specification depicted and noted in the Structure Details of Exhibits 2 and 4 submitted by ES. Structure 87 will not be replaced as part of this crossing."
2023, February 6: petition for crossing; "Eversource will maintain and operate the clearances of the crossings at a height no less than what is required by the 2012 National Electrical Safety Code (NESC, Table 232-1) which is 15.5 feet for neutral or ADSS wires over state-owned lands
2023, February 3: staff recommendation; 15.5 feet for neutral or ADSS wires of Cocheco River and public land.
2023, January 9: revised exhibit for crossing of Cocheco River
2023, January 9: exhibits for crossing; 795 ASCR 31/1 Coot, (2) 7#8 Alumoweld, (1) 64 fiber ADSS
1996,December 11: licensing of one ADSS