User Tools

Site Tools


m-183

This is an old revision of the document!


M-183 115kV line

map

2023, March 30: start of construction form

2023, March 30: DES permit waiving specific requirements of Env-Wq 1503.21(c)(2) and Env-Wq 1504.09,

2023, March 29: Alteration of Terrain application

2023, March 29: Environmental Resources map

2023, March 29: transmittal of final documents. "Additionally, project construction is planned to begin as soon as possible upon permit approval. With that, I wanted to inquire about the start of construction waiver and how/when that should be submitted?'

2023, March 16: PAC minutes; no comment from PAC on project

2023, March 16: PAC presentation

2023, February 14: "Although the Committee reviewed the project and plans and determined the minimal impact on the Cocheco River corridor would occur, it was noted that the project appeared to be outside the jurisdiction of the committee"

2023, February 16: email E$, Fish & Game, DES

2023, February 7: crossing license with revision and original license. "The proposed project encompasses a structure replacement whereby Structure 88 at the public water and Structures 81 through 85 at the state-owned land crossing span are to be replaced with a weathering steel equivalent having the design and specification depicted and noted in the Structure Details of Exhibits 2 and 4 submitted by ES. Structure 87 will not be replaced as part of this crossing."

2023, February 6: petition for crossing; "Eversource will maintain and operate the clearances of the crossings at a height no less than what is required by the 2012 National Electrical Safety Code (NESC, Table 232-1) which is 15.5 feet for neutral or ADSS wires over state-owned lands

2023, February 3: staff recommendation; 15.5 feet for neutral or ADSS wires of Cocheco River and public land.

2023, January 9: revised exhibit for crossing of Cocheco River

2023, January 9: exhibits for crossing; 795 ASCR 31/1 Coot, (2) 7#8 Alumoweld, (1) 64 fiber ADSS

2010, October 15: staff recommendation; "That crossing has been licensed by the Commission (see Order No. 12,219 in Docket 76-22). PSNH also received a license from the Commission for the fiber optic cable it installed and maintains at the same crossing location (see Order No. 22,454 in Docket DE 96-370). PSNH states that it needs to uprate the M-183 line conductors to increase the power transfer capability of the line in order to meet the increased load growth in the seacoast are of New Hampshire."

2010, September 23: revised petition to cross the Cocheco River in Dover

2010, August 27: petition to cross Cocheco River in Dover

2009, October 7: Order Nisi granting license

2009, September 30: staff recommendation; "The three phase conductors will be 795 kcmil ACSR with a 26/7 stranding"

2009, July 2: petition to cross the Bellamy River

1996,December 11: licensing of one ADSS

m-183.1712423084.txt.gz · Last modified: 2024/04/06 13:04 by sigridundset

Donate Powered by PHP Valid HTML5 Valid CSS Driven by DokuWiki