T-198 115kV line
2022, March 28: Start of Construction form
2022, February 7: Stamped AoT page
t198_completion_of_construction_notification.pdf
t198_aot_permit_application.pdf
t198_ground_and_surface_aot_overlay_1-2-2022.pdf
t198_des_permit_with_waivers.pdf
December 2021: order of notice
October 2021: Keene Conservation Commission
2021 presentation to PAC, 64 out of 154 structures replaced, $19.1 m.