T-198 115kV line
2023, February 3: Notice of completion of construction
2022, March 28: Start of Construction form
2022, March 28: DES permit waiving specific requirements of Env-Wq 1504.09,
2022, February 7: Stamped AoT page
2022, February 7: Alteration of Terrain application, GZA
2022, January 28: Permit for crossings granted
2022, January 2: Ground and Surface Water overlay maps
December 2021: order of notice
2021, December 15: Presentation to PAC, 64 out of 154 structures replaced, $19.1 m.
2021, December 9: DOE Inter-departmental communication
2021, November 24: E$ petition for river crossings
2021, November 15: Keene Conservation Commission
2021, July 25: E$ petition attachments also dated 12/2016
2013: Revised appendices a-k, 24 fiber ADSS
2012, October, proposed reliability upgrade
2008, October 1: Order Nisi granting crossing
2008, October 1: staff recommendation
2008, September 30: PSNH response to commission questions
2008, September 12: petition for crossing-installation of OPGW, reliability
2008, September 2: Eversource Agreement with DOT and easement deed