T-198 115kV line

2023, February 3: Notice of completion of construction

2022, March 28: Start of Construction form

2022, March 28: DES permit waiving specific requirements of Env-Wq 1504.09,

2022, February 7: Stamped AoT page

2022, February 7: Alteration of Terrain application, GZA

2022, January 28: Permit for crossings granted

2022, January 2: Ground and Surface Water overlay maps

December 2021: order of notice

2021, December 15: Presentation to PAC, 64 out of 154 structures replaced, $19.1 m.

2021, December 9: DOE Inter-departmental communication

2021, November 24: E$ petition for river crossings

2021, November 15: Keene Conservation Commission

2021, July 25: E$ petition attachments also dated 12/2016

2013: Revised appendices a-k, 24 fiber ADSS

2012, October, proposed reliability upgrade

2008, October 1: Order Nisi granting crossing

2008, October 1: staff recommendation

2008, September 30: PSNH response to commission questions

2008, September 12: petition for crossing-installation of OPGW, reliability

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008: Profile of crossing

2008, September 2: Eversource Agreement with DOT and easement deed

1995, September 6: The crossing of the T-198 line, as identified in Appendix 3 of the petition and on drawings D-7649-385/Exhibit 1 and D-7649-385/Exhibit 2, is over the Ashuelot River in Swanzey, NH