v-191
This is an old revision of the document!
V-191 115kV line, built in 2005
2022, June 2: AoT stamped page
2022, June 21: Environmental Resources map
2022, June 17: DES, Fish & Game and contractor emails
2022, May 16: Fish & Game recommendations, email
2021, October 20: Revised presentation to PAC
2021, after October: DOE order of hearing on crossing petition
2021, May 7: exhibits for crossing petition, also dated December 2016
2021, October 20; PAC presentation, replace 41 out of 60 structures at $11 m.