A-111 115kV transmission line

2023, May 31: ISO approval of Transmission Cost Allocation

2023, March 14: NEPOOL approval of $100 m.+ for A-111 , E-115 and Z-180 for Transmission Cost Allowance

2023, March: request to NEPOOL for TCA

March 3, 2022 New Hampton Selectboard minutes. E$ wants work to be allowed 7 days a week, 7:00 am to 7:00 pm. Dump trucks are delivering gravel for road building and there will be drilling.

2022: Start of Construction notice

2022, January 21: DOE crossing permit; six crossings

2021, October 21: crossing license for nine structure replacement, reconductoring and OPGW, William H. Thomas State Forest and Pemigewasset River in Hill and Hampton

2021, October 5: Order Nisi for crossing of William Thomas state forest and Pemigewasset River in Hill and New Hampton

2021, September 3: DES permit with waivers

2021, August 21: AOT permitting plan. "Work pad restoration will begin following line construction completion. Work pads will be covered with topsoil, seeded, and mulched."

2021, August 19, Application to NEPOOL for TCA. $33. m. Rebuilding line at the same size is not presented as an alternative. No pole inspections submitted. Described as reliability and asset condition project

2021, July: Project construction fact sheet citing reliability

2021, July 23: email from SEC chair to easement encumbered landowner with dead link to SEC document

2021, July 21: Minutes of SEC meeting where A-111 rebuild was determined not to be a sizeable change

2021, July 15: ISO determination of no problems with interconnection

2021, June 25: staff recommendation; nine wood structures replaced with steel, existing conductors will be replaced with (3) new ACSS 1272 54/19 kcmil conductors. Two existing shield wires will be replaced with (2) 48 fiber optical ground wire (OPGW)

2021, June 21: staff recommendation

2021, June 6: petition for crossing the Pemigewasset River in Hill and New Hampton, and William H.Thomas State Forest: "The proposed project for the A111 encompasses a full line rebuild."

2021, June 2: petition for crossing; exhibits: two 48 fiber .646 OPGW, steel structures, 1272 ACSS 54/7 conductor

2021, May 28: Eversource "brief" to SEC on "upcoming maintenance" (complete rebuild) of A-111 line

2021, May 26: AoT application and DES permit with waivers

2021, May 24: Draft minutes of SEC public meeting re. A-111

2021, May 19: NHB report

2021. April 16: SEC response to Eversource submission.

2021, April 8: Submission to SEC in which Erik Newman states: "The project was presented to ISO New England at the December 2020 ISO Planning Advisory Committee (PAC) meeting where it was also approved by ISO at the same meeting"

2021, March 9: inspection permit DES

2020, December 16: Minutes of PAC presentation meeting

2020, November 12: license for crossing

2020, October 22, revised staff recommendation; '“This crossing was previously licensed by the PUC pursuant to Order 12,219 in Docket # DE 76-22 issued March 12, 1976.” should have read “This crossing was previously licensed by the PUC pursuant to Order 12,219 in Docket # DE 76-22 issued April 21, 1976."

2020, October 16: supplemental petition with 1976 crossing date corrected

2020, September 4: staff recommendation; ES’s existing A111 line is not being relocated as result of this project using the existing conductors. The existing wood structure # 79 is being replaced with (3) steel pole structures due to age and environmental damage.

2020, March 31: petition to cross Pemigewasset River in Hill and New Hampton, red cedar structure 79 requires immediate replacement, steel, no conductor or ground wire changes

2020, March 31: Pemigewasset River crossing petition exhibits, 336.4 ASCR 26/7, 7#8 alumoweld static lines, 85' and 95' structures, 37.4' clearance

December 2020 Asset Condition PAC presentation

November 2020, petition for amended license

2015: "The load and added local generation in this area has not required the upgrading of either line."