307 345kV line
2023, May 23: DES permission for alteration of terrain with waivers
2023, Fish & Game restrictions on work
2023, March : license to cross
2021, March : staff recommendation
2023, March 7: crossing application
2022, June 16: e-mail with restrictions on work
2023, May 23: DES permit with waivers
2023, May 23: Start of construction notification
2023, March 23: Oyster River Local Advisory Committee comments
2023, March 23; Lamprey River LAC find with project
2023: March 13: license for river crossings, Pistaqua, Bellamy, Oyster and North Rivers
2023, March 12: letter to Lamprey River LAC
2023, March 10: DOE recommendation
2023, March 7: Eversource application for river crossing
2023, February 22: Lamprey River LAC to DES
2023, February 1: AOT checklist
2023, January 23: exhibits for DOE showing river crossing
2022, June 15, presentation to PAC
2019, February 11, submission to NEPOOL
2019, November 26, Durham permitted use
2019, December 11: Durham town planners review
2019, May 17: river crossing exhibits, two alumoweld static/ground lines, Lamprey River
2017, December presentation to PAC, replacement of 47 out of 145 poles.
2017, December 17, Deerfield Conservation Commission minutes