E-115 115kV Line $64 million
2023, March: request to NEPOOL for TCA
Road and wetlands matting on ROW and new structures, conductor and OPGW
Large truck hauling flatbed on wetland matting and road in ROW.
Excavator, gravel truck and other heavy machinery on ROW
2022, October 19; PAC presentation
2022, June 27: Final TCA E-115
2022, June 23; start of construction letter
2022, June 4, Alteration of Terrain plans amendment
2022, May 12: Access and permitting plans
2022, April 22: DES permit with waivers
2022, April 22: Start of Construction
2022, March 22: Alteration of terrain plans first page stamped
2022, March 1 AoT first page stamped
2022, February 21: Surface and Groundwater overlay maps, GZA
2022, January: license granted
2022, January: staff recommendation
2022: Eversource Transmission Cost Allocation application
December 2021, petition attachment, 12/2016 original date, pole heights 52'-106'
2021, July 15: no impact from interconnection