X-178 115V Line, built in 1948-9 with 336 ASCR, Streeter Pond Tap to Whitefield “upgraded” to 795 ASCR in 1969 when U-199 is built, Beebe River to Streeter Pond tap “upgraded” to 795 ASCR in 1986.
Listed as cancelled in April 2024 Asset Condition Project list.
Pole height increases, WMNF, Lincoln, Woodstock, Easton and Sugar Hill
2024, April 12: Eversource delays its May PAC presentation
2024, April 9: kp questions on Eversource Small Projects Day application to WMNF
2024, April 7: comment on Eversource and FirstLight
2024, April, 2: PAC responses to stakeholder comments
2024, March 20: kp letter to PAC and Eversource re. percent of category c poles
2024, March 20: kp letter to PAC re. OPGW
2024, March 20: Maine PUC comments
2024, March 15: NESCOE comments
2024, March 15: k. pastoriza alternatives to project proposal
2024, March 18, k pastoriza question re structure locations (incorrectly dated)
2024, March 9: k pastoriza request for Category C POLE locations
2024, March 1: Questions on X-178
2024, February or March, posted after 2/28 PAC meeting: PAC "Guidelines" for public comments
2024, February 27: kp question on X-178 presentation to the PAC document
2024, February 27: kp letter to PAC; X-178 is not an asset condition project
2024, February 26 (dated): Eversource response to k. pastoriza questions.
2024: Environmental Permitting Planset, Easton, no wetlands scientist stamp.
2024, February; Reel Brook Trail to be used as access road, pending WMNF approval, section 1
2024, February; Reel Brook Trail to be used as access road, pending WMNF approval, section 2
2024, February 29: PAC meetings fail to ensure adequate project review
2024, February 27: Questions on Eversource PAC presentation
2024, February 28: Eversource document for presentation to PAC
2024, January 18: kp questions on structure locations
2024, January 6, cover letter for wetlands permit application, Dalton
2024, January 3: Easton Conservation Commission draft minutes
January 6, 2023: Eversource presentation to Easton Conservation Commission with commentary
January 3, 2024: Eversource presentation to Easton Conservation Commission
2023: smooth green snake flyer
2023, October 5: Fish & Game and Eversource email
2023, September 7: Fish and Game and Eversource email
2023, September: X-178 crossing of Bog Pond
2023, September: view of Lafayette
2023, September: view of Mt. Wolf
2023, September: Bog Pond and east side of Old Kinsman Notch. X-178 line below cliffs on left.
2023, September: X-178 line below Cliffs, and Bog Pond
2023, September: Bog Pond and X-178, South Kinsman behind
2023, September: Cliffs with X-178 below, and Bog Pond
2023, August 23: letter to PAC and Eversource
2023, August 1; Campton, Thornton and Woodstock DRAFT proposed construction plans
2023, August 1; North Woodstock to Sugar Hill DRAFT proposed construction plans
2023, August 1; Sugar Hill, Bethlehem, Dalton, Whitefield DRAFT proposed construction plans
2023, Inspection/Treatment tags on 1948 section of line
2023, July 3; drone image X-178
2023, July 23; drone image x-178 no road
2023, May letter to ISO re X-178 and Asset Condition problem
2023, June; questions for Eversource
2023, May 24; response to Eversource answers to questions
2023, May; questions for Eversource
2023, May 16: Fish and Wildlife letter re. endangered species
2023, April 22: "Dear Neighbor" letter
2023, April; Project Fact Sheet sent to landowners claiming reliability
2023, April 14; "Confidential" Project information sent with the email above.
2023, April 7: Project presentation to WMNF (?)
2023, April 13: Archaeological survey proposal, WMNF
2022, September 19: Survey Postcard
2021, February 18: Transmission line aerial overview plans, GZA
2020, January 30: Aerial overview plan
2018, October 17; PAC submission, replace 56 structures out of 570 at $11.2 million, later cancelled
2017 river crossing application, no mention of pole condition problems.
circa 2017 crossbar and insulator replacement
2016: Bog Pond Scenic Area proposal rejected by WMNF
2016: Bog Pond Scenic Area procedural history
Winco Longline job hazard analysis
PAR X-178 Health and Safety Plan
2014: Eversource valuation of ROW and infrastructure in Easton
2013, May 22: Northern Pass and WMNF Special Use Permit requirements
NP Special Use Permit info. for WMNF with map showing where Eversource has no ROW
2013; found poem: Muntz WMNF special use permit application
Bog Pond area with poles dumped in 1986 "upgrade"
2013, September 5: Northern Pass amended attachment to Special Use Permit
1987 Pemigewasset crossing, North Woodstock
1986 'upgrade' paid for by Hydro-Quebec
Pesticides used on ROW until 1985
1970, November 13: Special Use Permit for powerline in Woodstock
1970, March 25: FS to DOT re Special Use Permit for powerline in Woodstock.
1970, February 19: Plymouth Record on powerline relocation
1970, February 10: Forest Service denies PSNH special use permit for new line
1950 PSNH transmission map showing X-178
1948, June 15: WMNF SUP permit for X178, "part of a similar line from Northumberland to Woodstock"
1945: Forest Service suggests Bog Pond rather than Coppermine Trail