T-198 115kV line
2023, February 3: Notice of completion of construction
2022, March 28: Start of Construction form
2022, March 28: DES permit waiving specific requirements of Env-Wq 1504.09,
2022, February 7: Stamped AoT page
2022, February 7: Alteration of Terrain application, GZA
2022, January 28: Permit for crossings granted
2022, January 2: Ground and Surface Water overlay maps
December 2021: order of notice
2021, December 15: Presentation to PAC, 64 out of 154 structures replaced, $19.1 m.
2021, December 9: DOE Inter-departmental communication
2021, November 24: E$ petition for river crossings
2021, November 15: Keene Conservation Commission
2021, July 25: E$ petition attachments also dated 12/2016
2008: petition for crossing-installation of OPGW, reliability