345kV Line 326
2022, August 19: retirement of 326 line RAS E$ to ISO
2022, August 5: Start of construction notification
2022, July 29: DES permit waiving
specific requirements of Env-Wq 1503.12(d)(1&2), Env-Wq 1503.21(d)(6&7), and Env-Wq 1504.09,
2022, July 18: "NHFG wants emphasize that this is an extremely sensitive area with rare animals known to make extensive use of the
ROW and surrounding habitat, as well as an area of past compliance issues with Eversource."
2022, June 20: New Hampshire Heritage Bureau email
2022, June 15 presentation to PAC
2022, April 15: application to Town of Hudson for conditional use permit
2022, April 11: Order of Notice,line has three ACSR 850.8 Kcmil phase conductors, a single 7#8 Alumoweld static wire and a single 0646" OPGW wire will be transferred to the replacement structures.
2022, March 29: AoT application, GZA
2022, March ground and surface water AOT
2022, March: disturbed areas AOT
2022, March 29: petition for crossings
2022, March 29: petition attachments
2022, March 17: Order re. petition for crossing rivers/public lands
2022: staff recommendations
2022: license
line diagram
2021, May 4: Order, The Company proposes to replace existing Structure 5 with a newly constructed steel support structure. The three existing conductors and the existing static wire and optical ground wire (OPGW) on the line will be transferred to the new structure. The Company also seeks an after-the-fact license for the 2018 replacement of Structure 4 at the same crossing location
2017, December presentation to PAC, replacement of 43 out of 166 poles.
2016, January 7: TCA approval, apparently reliability
2012, October, proposed reliability upgrade
psnh_cost_per_mile_115kv.jpg