326

345kV Line 326

2022, August 19: retirement of 326 line RAS E$ to ISO

2022, August 5: Start of construction notification

2022, July 29: DES permit waiving specific requirements of Env-Wq 1503.12(d)(1&2), Env-Wq 1503.21(d)(6&7), and Env-Wq 1504.09,

2022, July 18: "NHFG wants emphasize that this is an extremely sensitive area with rare animals known to make extensive use of the ROW and surrounding habitat, as well as an area of past compliance issues with Eversource."

2022, June 20: New Hampshire Heritage Bureau email

2022, June 15 presentation to PAC

2022, April 15: application to Town of Hudson for conditional use permit

2022, April 11: Order of Notice,line has three ACSR 850.8 Kcmil phase conductors, a single 7#8 Alumoweld static wire and a single 0646" OPGW wire will be transferred to the replacement structures.

2022, March 29: AoT application, GZA

2022, March ground and surface water AOT

2022, March: disturbed areas AOT

2022, March 29: petition for crossings

2022, March 29: petition attachments

2022, March 17: Order re. petition for crossing rivers/public lands

2022: staff recommendations

2022: license

line diagram

2021, May 4: Order, The Company proposes to replace existing Structure 5 with a newly constructed steel support structure. The three existing conductors and the existing static wire and optical ground wire (OPGW) on the line will be transferred to the new structure. The Company also seeks an after-the-fact license for the 2018 replacement of Structure 4 at the same crossing location

2017, December presentation to PAC, replacement of 43 out of 166 poles.

2016, January 7: TCA approval, apparently reliability

2012, October, proposed reliability upgrade

psnh_cost_per_mile_115kv.jpg