379 345kV line
2023, January 19, presentation to PAC, replace shield wire
2022, November 8: license for crossing
2022, October 24: application for crossing
2022, November 2: staff recommendation
2022, September 20: diagrams of crossing in Hinsdale, also dated 12/2016.
2022, July 8: petition for crossing
2022, July 11: start of construction notification to DES
2022, May 19: license for crossing
2022, May 16: AOT permit application
2022, May 6, Alteration of Terrain application
2022, May 5: permitting plan set
2022, May 5: Alteration of Terrain, stamped first page
2022, April Chester Public Hearing Notice
2022, March 16, water crossing diagrams, also dated 12/2016. Required 20' clearance exceeded by 45'
2017, December presentation to PAC, replacement of 54 out of 169 poles.