A-152 115kV line

2023, December 21; k. pastoriza questions on E$ PAC presentation

2023, December 20: E$ presentation to the PAC; replace 18 B: "Minimal Defect – Monitor Degradation" and 3 C: "Moderate Defect – Repair or Replace under next maintenance" (8 years?) structures; $5.8 m.

2022, June 30: complete DE-22-049 document listing E$ proposed spending

2022, March 28, DES permission to alter terrain waiving specific requirements of Env-Wq 1504.09,

2022, February 8: Original AoT application

2022, February 7: Stamped Alteration of Terrain plans

2022, January: Surface and Groundwater overlay maps

2022, January 18: license granted

2021, October 20: undated revision to 10/20/21 PAC submission, laminated wood phase 2 revision 1 replace 72 out of 242 structures at $15.3 m.

2021, December 16: Order Nisi

December 2021 staff recommendation,steel poles 65'-79'

November 12, 2021 crossing petition, "The current maintenance project which is the subject of this petition will replace wood structures 1 through 72 that were installed in 2008 with steel structures."

November 2021 Keene Conservation Commission minutes

September 2021 crossing exhibits, Keene, Swanzey, Winchester. Monopoles with 64 fiber and H-frames with 64 fiber and 7#8 Alumoweld.

2020, September 11: order granting crossings. "Staff’s recommendation proposed expanding the scope of the licenses to include an existing fiber optic telecommunications line, which Eversource already maintains on its existing overhead line structures across the entire span of the crossings at issue. The Company references the fiber optic cable in its supplemental petition.'

2020, April 29: supplement to April 11 petition for crossing. "No conductor, shield wire or neutral wire will be replaced as part of this project; instead, existing conductors and wires will be transferred to the new structures (Str. 75, 76, 77, 78, 79, 80, 81, 82, 83, 153, 175), which will be a steel structure replacement of the original wood structures"

2019, September 20: petition for crossing, Winchester and Swanzey, No conductor, shield wire or neutral wire will be replaced as part of this project; instead, existing conductors and wires will be transferred to the new structures (Str. 75, 76, 77, 78, 79, 82, 83, 152, 153, 154, 175, 176), which will be a steel structure replacement of the wood structures.

2019, September 20: Petition for crossing, Winchester and Swanzey exhibits, two 7#8 Alumoweld, one ADSS .636, 795 ASCR 36/1 Coot

2018, October 17; PAC submission, replace 29 structures at $6.1. million

2012, October, proposed reliability rebuild

2008: Petition for crossing, reliability upgrade

2008: Profile Ashuelot River, Swanzey

2008: Profile Ashuelot River, Swanzey

2008: Profile Ashuelot River, Keene